Symptom
Crystal Report Schedule fails intermittently for few parameter values and throws error message "Object failed to run due to an error while processing on the Job Server".
Following error messages could be seen in the windows event viewer:
"The scheduler component failed the object identified by 52335883. The job associated with the object was unresponsive"
"The schedule result provided by the Job Server for the object identified by 52334760 is invalid"
"Subprocess (Job Server Child) could not be started. Reason: Couldn't get IJob interface or writing IAudit: Pipe exception. Reason: jobserverchild (procprogram, 2, Could not send request to child [13860] (timeout = [60000]ms, request time span = [2013])"
Environment
SAP BusinessObjects Enterprise XI 3.1
Reproducing the Issue
Login to Infoview or CMC with Enterprise user.
Schedule a crystal report having multiple subreports and dynamic prompts in it.
Cause
Unable to retrieve data for the provided prompt values due to incorrect database configuration.
Resolution
Open the affected report into Crystal Report designer.
Refresh the report with the same prompt values with which we are unable to schedule the report.
It wont bring any data after refresh completes.
Update the data source from designer and save it back into enterprise.
Subscribe to:
Post Comments (Atom)
Sonarqube Upgrade from 9.4.4 to 9.9.4 LTS
Issue: 1) Java hasbeen upgraded from 11 to Open JDK 17. And Sonarqube is upgraded from 9.4 to 9.9.4. 2) After the upgrade sonarqube servic...
-
Disaster Recovery for SAP Business Objects 4.1/SAP Crystal Enterprise 2013 Prerequisites: 1. File Store Input and Output folders 2. Back...
-
Username: test Environment : Linux $usermod -d /usr/test -m test ## Here "test" is a user and /home/test is directory which w...
-
• The default report job server children for Windows have been changed in BusinessObjects Enterprise XI from OUTPROC to MIXEDPROC. This caus...
No comments:
Post a Comment